Building applications

To obtain building approval, an application must be lodged with the permit authority that has responsibility for the area in which the building is (or is intended to be) located.
As a permit authority under the Building Act 2011, the City controls the construction, occupation and demolition of buildings and incidental structures through the granting of building, demolition or occupancy permits and building approval certificates and the enforcement of compliance with permits.

Application information

Register or sign in

To submit an application, you will need to register or sign in for a mySouthPerth account. Click the Register and Sign In option at the top right of this page to proceed.
For assistance with your mySouthPerth account, visit our information page.

Already signed in?

If you see your initials at the top right-hand corner of this page, you are already signed in.

Submit an application

To submit an application, proceed below.

Before you begin

Prior to commencing the application via the link below, ensure you have an electronic copy (eg scan) of the following documentation prior to completing the application process:
  • Application for Building Permit Form, either certified or uncertified
  • One set of architectural and structural drawings, site plan and details (refer below for further information)
  • Home Indemnity Insurance (HII) if cost in excess of $20,000 (unless it is an excluded development - refer above).
You will be required to attach this information during the application process.

Application attachments

Please ensure you are attaching all plans, materials and supporting information relevant to the application as part of your initial lodgement. Any omissions or additional materials will be required to be sent as separate emails, which will be limited to standard email size limitations (eg 10MB).
I have a Certificate of Design Compliance (BA01)
I DO NOT have a Certificate of Design Compliance (BA02)

Post lodgement process

Once your application is lodged, the following steps will apply:
  • Your application will be reviewed to ensure all required information/documentation has been provided. You will be contacted if anything is missing
  • When all documentation has been received, the lodgement process will be complete
  • The application will then be assessed and the following timeframes apply:
  • Certified applications can take up to 10 business days from acceptance for a decision
  • Uncertified applications can take up to 25 business days from acceptance for a decision.
Please take the time to check that the application is complete. An incomplete application may be returned and the fees forfeited.